MRT’s first contract runs into controversy

April 15, 2011
KUALA LUMPUR, April 15 — The owners of the Klang Valley Mass Rapid Transit (MRT) will award their first major contract today for an independent check engineer (ICE) chosen by the government and who will be paid two per cent of the undetermined project cost, which is reportedly above market rates.

The Malaysian Insider understands that the consortium of HSS Integrated Sdn Bhd, Hong Kong’s MTR Corp Ltd and Canadian SNC-Lavalin is likely to land the contract despite being rejected by Syarikat Prasarana Berhad (SPNB) earlier for not putting a price to its brief — which usually costs up to 0.8 per cent of the total project.

The total project cost for the MRT is estimated at RM36.6 billion for three rail lines through the Klang Valley when it was first proposed two years ago but that projection did not include cost of land and also rolling stock for the MRT.

“The SPNB board will meet today to approve the decision made by the exco at the Finance Ministry level. They will have to abide by the decisions as the money is paid by the government,” a source told The Malaysian Insider.

It is understood that the figure for the ICE could go as high as RM720 million based on the initial cost of the country’s largest infrastructure project.

But the source said the two per cent payment for the cost appeared steep against the industrial convention of just under one per cent for sub-contractors.

It is also learnt that SPNB should have ruled out HSS Integrated as it had an existing working relationship with MRT project delivery partner (PDP) MMC-Gamuda, though the current double-tracking rail project in north Malaysia.

“When the request for information was sent out before last Christmas, it stated clearly that the winning ICE should not have an existing relationship with the PDP. HSS has but it has been conveniently overlooked,” another source told The Malaysian Insider.
SPNB chief executive Shahril Mokhtar said last week a one-stop technical committee will evaluate the bids before recommending it to a Finance Ministry committee that will decide on the contract awards.

“It’s their money so they decide,” Shahril said, adding this was different from the current LRT extension works which is funded by bonds issued by SPNB.

SPNB had also not finalised the financing and project manager’s fees for the MRT although planning has started for initial civil engineering work to begin in November.

Regulator Land Public Transport Commission (SPAD) had said the Finance Ministry has set up a special purpose vehicle (SPV) to raise funds for the project but had admitted the method has yet to be determined.
The SPNB chief had also said some 100 firms have applied for pre-qualification for the 16 packages in the elevated part of the 51km-long MRT; the deadline for pre-qualification ended on April 13.

The MRT is the country’s biggest infrastructure project and also the largest National Key Economic Area (NKEA) project under Prime Minister Datuk Seri Najib Razak’s New Economic Model (NEM).

The massive project is expected to generate 130,000 jobs in its five-year construction phase. The government hopes that more than half of the population in Greater KL will use the public transport system to prevent traffic congestion.


MRT: Kontrak pertama dianugerah hari ini, cetus kontroversi

April 14, 2011
KUALA LUMPUR, 14 April — Pemilik Aliran Transit Massa (MRT) Lembah Klang akan menganugerahkan kontrak utama pertamanya hari ini kepada Jurutera Pemeriksa Bebas (ICE) yang dipilih kerajaan dan akan dibayar dua peratus daripada nilai projek, yang kos projek masih belum muktamad - di mana fi itu didakwa lebih tinggi berbanding kadar pasaran.

The Malaysian Insider difahamkan konsortium HSS Integrated Sdn Bhd, MTR Corp Ltd dari Hong Kong dan syarikat Kanada SNC-Lavalin, dijangka akan memperoleh kontrak itu meskipun telah ditolak oleh Syarikat Prasarana Berhad (SPNB), pemilik projek sebelum ini.

Kos keseluruhan projek MRT itu dianggarkan RM36.6 bilion ketika diumumkan dua tahun lalu tetapi ia tidak termasuk kos tanah.

Kos terbaru yang diumumkan dipercayai mencecah lebih RM50 bilion.

“Lembaga SPNB akan bertemu hari untuk meluluskan keputusan yang dibuat oleh exco di peringkat Kementerian Kewangan. Mereka (SPNB) perlu ikut keputusan itu memandangkan wang itu dibayar oleh kerajaan,” kata sumber kepada The Malaysian Insider.

Difahamkan kadar itu boleh mencecah RM720 juta berdasarkan pada fi yang diperlukan bagi projek tersebut.

Bagaimanapun sumber berkata bayaran dua peratus ke atas kos kelihatan bertentangan dengan konvensyen industri yang lazimnya di bawah paras satu peratus bagi subkontraktor.

Juga difahamkan konsortium juga mengetepikan HSS Integrated memandangkan ia mempunyai hubungan kerja semasa dengan penyedia projek  MMC-Gamuda menerusi projek landasan kereta api berkembar di utara Malaysia.

“Apabila permintaan untuk maklumat dihantar sebelum sambutan Krismas lalu, ia dengan jelas menyatakan bahawa (pihak yang) memperoleh anugerah ICE tidak harus mempunyai hubungan semasa dengan penyedia projek.

“HSS ada tetapi secara konvensyen telah dipandang mudah,” kata satu lagi sumber.

Minggu lalu, Ketua eksekutif SPNB Shahril Mokhtar berkata, jawatankuasa teknikal sepusat akan menilai bidaan-bidaan sebelum mengesyorkan kepada jawatankuasa Kementerian Kewangan yang akan memutuskan penganugerahan kontrak.

“Itu wang mereka, maka mereka akan memutuskan,” kata Shahril.

Minggu lalu, The Malaysian Insider membawa laporan bahawa Putrajaya masih belum memuktamadkan aspek pembiayaan dan fi pengurus projek MRT ini meskipun  perancangan telah dimulakan bagi kerja-kerja kejuruteraan sivil yang akan dilakukan November ini.

Ketua Pegawai Eksekutif Suruhanjaya Pengangkutan Awam Darat (SPAD) Mohd Nur Kamal berkata, hanya Surat Anugerah (LoA) telah dikeluarkan kepada MMC-Gamuda selaku Rakan Pelaksana Projek (PDP) tetapi belum memuktamadkan soal fi.

“Kami bekerja kuat untuk memuktamadkannya dan ia akan diumumkan sebelum kerja-kerja pecah tanah Julai ini,” kata beliau pada sesi taklimat kepada pemberita semalam.